Data Quality Guidance

Data quality is assigned using numerical scores of 1-5. In EPA’s pedigree system, data that are of higher quality receive lower scores. The matrices below are replicated from those published by EPA.

Process level data quality

Indicator1 (highest)2345 (lowest)
Process ReviewDocumented reviews by a minimum of two types[1] of third party reviewersDocumented reviews by a minimum of two types of reviewers, with one being a third partyDocumented review by a third party reviewerDocumented review by an internal reviewerNo documented review
Process Completeness>80% of determined flows have been evaluated and given a value60-79% of determined flows have been evaluated and given a value40-59% of determined flows have been evaluated and given a value<40-59% of determined flows have been evaluated and given a valueProcess completeness not scored

Flow level data quality

Indicator1 (highest)2345 (lowest)
Flow ReliabilityVerified[2] data based on measurementsVerified data based on a calculation OR non-verified data based on measurementsNon-verified data based on a calculationDocumented estimateUndocumented estimate
Temporal CorrelationLess than 3 years of difference[3]Less than 6 years of differenceLess than 10 years of differenceLess than 15 years of differenceAge of data unknown or more than 15 years
Geographical CorrelationData from same resolution and same area of study.Within one level of resolution and a related area of study [4]Within two levels of resolution and a related area of studyOutside of two levels of resolution but a related area of studyFrom a different or unknown area of study
Technological CorrelationAll technology categories[5] are equivalentThree of the technology categories are equivalentTwo of the technology categories are equivalentOne of the technology categories is equivalentNone of the technology categories are equivalent
Data CollectionRepresentative data from >80% of the relevant market[6], over an adequate period[7]Representative data from 60-79% of the relevant market over an adequate period or representative data from >80% of the relevant market over a shorter period of timeRepresentative data from 40-59% of the relevant market over an adequate period or representative data from >60-79% of the relevant market over a shorter period of timeRepresentative data from <40% of the relevant market over an adequate period or representative data from >40-59% of the relevant market over a shorter period of timeUnknown or data from a small number of sites and from shorter periods
Footnotes
  1. Types are defined as either industry or LCA experts

  2. Verification may take place in several ways, e.g. by on-site checking, by recalculation, through mass balances or crosschecks with other sources. For values calculated from a mass-balance or another verification method, an independent verification method must be used in order to qualify the value as verified.

  3. Temporal difference refers to the difference between date of data generation and the date of representativeness as defined by the scope of the project.

  4. A related area of study is defined by the user and should be documented in the geographical metadata. The relationship established in the metadata of the unit process should be consistently applied to all flows within the unit process. Default relationship is established as within the same hierarchy of political boundaries (e.g. Denver is within Colorado, is within the USA, is within North America).

  5. Technology categories are process design, operating conditions, material quality, and process scale.

  6. The relevant market should be documented in the DQG. The default relevant market is measured in production units. If the relevant market is determined using other units, this should be documented in the DQG. The relevant market established in the metadata should be consistently applied to all flows within the unit process.

  7. Adequate time period can be evaluated as a time period long enough to even out normal fluctuations. The default time period is 1 year, except for emerging technologies (2-6 months) or agricultural projects >3 years.